Questions buyers ask before the first order
Answers below are the commercial facts as they stand, not marketing copy. Where a number depends on your tube, it says so.
What is the minimum order quantity?
One unit. Machines and fittings both start at 1 unit, because the limit is the tooling set rather than a container load.
What is the lead time?
1–3 weeks for a standard machine. Custom dies are quoted separately because the die set is made against your tube data.
Which Incoterms do you work with?
EXW, FOB, CIF. For a first order, EXW lets you use your own forwarder; CIF is quoted when the destination port is known.
How do I pay?
T/T (bank transfer). Exact terms are confirmed on the proforma invoice before production starts.
Do I need to send samples?
Not for a standard machine, but a sample tube or a drawing of the end form shortens the check. The die set is selected from tube OD, wall thickness and material, so those three numbers matter more than the drawing.
Is the machine CE marked?
The KC-A01 ferrule pre-assembly machine carries a CE verification of conformity issued by ICR Co. Ltd (ICR/VC/HS240604, valid to 2029-06-03). That document is a voluntary verification, not an EU Declaration of Conformity — see the certificate page for the exact wording. Other models are quoted with their own documentation status.
Which standards do the fittings follow?
The technical documents reference DIN 2353, DIN EN ISO 8434-1, ISO 6149, SAE J518 / ISO 6162 flange practice and GB/T 3765. A standard number on a data sheet is a design reference, not a certificate.
Can you supply a complete line?
Yes. Cut, deburr, form or bend, pre-assemble, then test — the machines are made to be combined, and tooling is quoted as one package.
How are the machines shipped?
Wooden crate, sea freight by default. Machine size and packed size are listed on each product page so you can check the crate against your handling equipment.